Each milestone is worth $1200, except for the first milestone which is worth $2400. Payment for the 5th milestone is dependant on whether or not it is necessary to take a 5th week. This will e discussed at the proper time. Week 1 Discuss and finalize a working design. Find/build some layouts that will work with that design. Build a database schema. THQ will work with and provide feedback on this design. initial design -data types -user flow database design basic layouts (admin, wwe) Week 2 Using the database schema built the previous week, begin building assets and submissions. Begin tying these two types together. By the end of the week create assets that belong to submissions. Start creating user authentication and user types. basic functionality submission -CRUD -flush out data type basic functionality asset -CRUD -flush out data type MILESTONE 1 Design Assets that can be uploaded and assigned to a submission THQ approval of design and preliminary functionality. basic user login -flush out data type -install plugin -configure site -implement admin controls Week 3 We want to be able to log users and allow administrators to manage these users. Continue work on submissions and assets. By the end of the week, while not bug-free, submissions should be 90% working. Minor design update on user permissions with input from THQ. logging polish submissions polish assets reviewing of submissions MILESTONE 2 Users, logging Submission reviews THQ approval of user authentication, logging and submission reviewing. Week 4 This is a week to continue working on previously implemented features. Polish up submissions, user logging. Begin work on deployment. Any discussion with THQ about redefining features and milestones should happen here. polishing bug-fixing installation testing MILESTONE 3 Finished & installed THQ approval on everything implemented so far and agreement of no extraneous features. Week 5 (optional) If there are more features that get added to the design, this is time scheduled for it. The features may be implemented earlier, but this is the buffer time. MILESTONE 4 (buffer week if necessary) Complete THQ approval on everything implemented so far and agreement of no extraneous features.